CEDD signs contract for Open Space Development in Tung Chung New Town Extension (East) - Phase 1
On 11 April 2025, the Civil Engineering and Development Department signed a contract with Chun Wo - Build King Joint Venture for the Contract No. NL/2023/13 - Open Space Development in Tung Chung New Town Extension (East) - Phase 1.
LegCo Funding Approval
On 21 March 2025, the Finance Committee of the Legislative Council approved the funding application for Tung Chung New Town Extension – site formation and infrastructure works (Second Phase).
Click here for Paper PWSC(2024-25)21.
Public Works Subcommittee Meeting
On 19 February 2025, the Public Works Subcommittee of the Legislative Council was briefed on the funding application for Tung Chung New Town Extension – Site formation and infrastructure works (Second Phase).
Click here for Paper PWSC(2024-25)21.
Handover of public housing sites Area 133A, Area 133B and Area 133C
On 30 December 2024, Area 133A, Area 133B and Area 133C were handed over to Housing Authority for public housing development.
Panel on Development Meeting
On 26 November 2024, the Panel on Development of the Legislative Council was briefed on the funding application for Tung Chung New Town Extension—Site formation and infrastructure works (Second Phase).
Click here for Paper No. CB(1)1487/2024(05) and Presentation Material CB(1)1587/2024(03).
Islands District Council Meeting
On 10 September 2024, the IsDC was briefed on the latest status of the TCNTE project including the proposed phase 2 infrastructure works and open space development project.
Click here for Paper IDC paper No. 43/2024 and Attachments.
Handover of public housing sites Area 114 and Area 117
On 28 June 2024, Area 114 and Area 117 were handed over to Housing Authority for public housing development
Islands District Council Meeting
On 11 June 2024, the Traffic and Transport Committee of Islands District Council was briefed on the temporary traffic arrangement for construction of bridges of Tai Ho Interchange and road sign gantries under CEDD Contract No. NL/2020/07. Click here for T&TC Paper No. 28/2024.
Handover of public housing site Area 119
On 29 December 2023, Area 119 was handed over to Housing Authority for public housing development
Substantial completion of TCNTE - Reclamation and Advance Works
Contract No. NL/2017/03 Tung Chung New Town Extension - Reclamation and Advance Works was substantially completed on 10 January 2023
Island District Council Meeting
On 3 November 2022, the Islands District Council was briefed on the conceptual design of the Open Space at Tung Chung East (TCE) of the Tung Chung New Town Extension (TCNTE) Project. Click here for IDC Paper No. 51/2022 and Attachment.
Road Works at Ying Hei Road and Tung Chung Waterfront Road authorized
Road Works at Ying Hei Road and Tung Chung Waterfront Road was authorized on 14 October 2022 under Roads (Works, Use and Compensation) Ordinance (Chapter 370). Click here for Gazette Notice
Road Works at Ying Hei Road and Tung Chung Waterfront Road gazetted
Gazette of Road Works at Ying Hei Road and Tung Chung Waterfront Road was published on 2 June 2022 under Roads (Works, Use and Compensation) Ordinance (Chapter 370). Click here for Gazette Notice
CEDD signs consultancy agreement for Quantity Surveying Services for Open Space Development in Tung Chung New Town Extension (East)
On 1 April 2022, the Civil Engineering and Development Department signed a consultancy agreement with Arcadis Hong Kong Limited for the Agreement No. 9QK102 - Quantity Surveying Services for Open Space Development in Tung Chung New Town Extension (East).